2003 to Present : Infratrend Engineering Sdn. Bhd.
Managing Director
Aug. 2001 to Jan. 2003 : Tritex Containers (M) Sdn. Bhd.
- Maintenance Manager
-Scheduling, planning and managing for maintenance shutdown works with vendors, specialized contractors and maintenance crews. Preparation of daily routine maintenance work, weekly planned schedules and cost summary reports.
May 1996 to August 2001 : Transwater Engineering Sdn Bhd
(PKK Class A Contractor involved in Water &
Wastewater Engineering works)
-Project management, scheduling, procurement, supervisory and coordination of daily work schedules for water and wastewater construction industries. Also involved in start-up, pre-commissioning, testing & commissioning and endurance testing activities.
-Assistant Engineering Manager
Management Contractor for Indah Water Konsortium.
-Project Manager
Perbadanan Air Melaka
Execution and Commissioning of the Chin Chin Water Treatment Plant.
-Project Manager
Metropolitan Utilities Corporation/Lembaga Air Perak
Parit Extension works – Phase III
-Project Manager
Jabatan Bekalan Air Pahang
Bukit Tinggi Water Treatment Plant
Execution of Civil, Mechanical & Electrical Works.
Feb. 1996 to May 1996 : -Electrical & Instrumentation Project Engineer (Contract)
-Detail Engineering and designing work for Balder Topside Facilities for RPV Development for Esso Norge AS, Norway.
Sep. 1995 to Jan. 1996 : -Instrumentation Manager
Medium Density Fibreboard Plant,
Bintulu, Sarawak.
-Managing and coordination of all daily construction schedules and activities with all supervisors. Duties include making progress claims/invoices, variation work orders and correspondences to main contractor and client.
Feb. 1994 to Aug. 1995 : -Instrument Superintendent
Foster Wheeler (M) Sdn Bhd
Project Management Consultant for the Malaysia Liquidified Natural Gas No. 2.
-Inspection duties and reporting on the construction of MLNG (2) plant consisting of three modules in Bintulu, Sarawak. Supervisory duties included weekly highlights reporting, monitoring and reporting of contractor’s work progress. Work included punchlisting activities for Mechanical and Ready for Start-up completions, including the monitoring and auditing of contractor Q.C documentation records and surveillance of ongoing safety.
Apr. 1988 to Feb. 1994 : -Senior Instrument Designer
Brunei Shell Petroleum Co. Sdn. Bhd.
Brunei Darulssalam.
-Engineering and designing work include cable tray routing layouts, hook-ups, C.A.O loops & schematics, pneumatic & electrial control/shutdown schematics, fire & gas detection systems, cable schedules, material take-offs, fabrication details and various associated tasks.
April 1980 to March 1988 : -Senior Electrical Designer/Inspector of Works
KTA Tenaga (M) Sdn Bhd Consulting Engineers
-5 years experience in design and drafting of H.V./L.V. main intake sub-station layours, switchroom layouts, power & lighting schemes, lighting & earthing protection schemes, bus-ducting, cable ladder and trenching layouts. 5 years experience as an Inspector of Work, duties included site supervision, testing & commissioning of H.V./L.V. equipment and co-ordinating of contractor work schedules.
Project Involvement as an Inspector of Works :-
- Genting Highlands Resort
132/33/11kV main intake sub-stations & transmission lines.
- Tenaga Nasional Berhad (L.L.N.)
Central Kedah Valley 33kV sub-stations & transmission lines.
- Malayan Flour Mills (M) Sdn Bhd
33 kV main intake sub-station-modification works
- Hong Leong Property Management (M) Sdn Bhd
H.V. & L.V. electrical & telecommunication infrastructure project
1978 to March 1980 : -Electrical & Instrumentation Draftman/Clerk of Works
Borneo Air-Cond Engineering Sdn Bhd
Electrical & Instrumentation Contractor
-Design and drafting of loop diagrams, interconnection diagrams, control & shutdown schematics, panel/marshalling layours and diagrams, fabrication and detailed/workshop drawings.
Project Involvement :-
- Prai Power Station – Stage III Boiler & Turbine Cabling Contract
1977 to 1978 : Electrical Draftsman (Trainee)
Leun Wah Electric Co. Sdn. Bhd.
Electrical Contractor
-Drafting electrical & telecommunication drawings for high rise, industrial and commercial buildings.